RN33 Nyemba-Kabalo

Roads

Nameof the client : Governorate of Haut-Katanga
Description : Rehabilitation and modernization works of the RN33 Nyemba Kabalo road
Contractor : EGMF
Additional informations :

  • Construction of a single layer road of 185 km over a width of 6m.

  • Construction of a new mixed bridge in Luizi with a span of 41m and a width of 6m

  • Reinforcement of six existing bridges.

  • Construction of engineering structures (7 box culverts and 10 culvert crossings) for crossing watercourses.

    This project is divided into three sections:

    • 1st section = Nyemba – Nyunzu – 55km

    • 2nd section = Nyunzu – Luizi – 65km

    • 3rd section = Luizi – Kabalo – 65km

Tanganyika RN 33 Nyemba Kabalo RN 33 Nyemba Kabalo Laterite reloading RN33 Nyemba Kabalo